ANALISIS PENGARUH PENGGUNAAN BANK KAPASITOR TERHADAP RUGI-RUGI DISTRIBUSIPADA SISTEM PLTMH GUNUNG SAWUR 2 LUMAJANG
ANALYSIS OF THE EFFECT OF CAPACITOR BANK USAGEON DISTRIBUTION LOSSES IN THE GUNUNG SAWUR 2 MICRO-HYDRO POWER PLANT SYSTEM,LUMAJANG
disusun oleh ABDUL HAMID
Subyek: | Rugi-Rugi Distribusi Bank Kapasitor |
Kata Kunci: | Bank kapasitor rugi-rugi distribusi power factor ETAP Hasil |
[ Anotasi Abstrak ]
Penelitian inimenganalisis pengaruh penggunaan Bankkapasitor terhadap rugi-rugi distribusi pada sistempembangkit mikrohidro Gunung Sawur. Studi ini dilakukan untuk mengevaluasiefektivitas bank kapasitor dalam meningkatkan efisiensi sistem distribusi listrikdengan mengurangi rugi-rugi daya reaktif. Proses analisis dimulai dengan pengumpulanparameter dasar sistem, termasuk karakteristik generator, jenis kabel, dan beban, yangdiperoleh dari spesifikasi teknis serta pengukuran langsung di lapangan. Datayang diperoleh digunakan dalam perhitungan manual untuk menentukan parameterkunci seperti daya keluaran, efisiensi, dan kestabilan system kemudiandiimplementasikan dalam perangkat lunak ETAP guna melakukan simulasikelistrikan yang mencakup analisis aliran daya, kestabilan sistem, dan berbagaiskenario operasional dengan serta tanpa penggunaan Bank kapasitor. Dari hasilanalisis regulasi tegangan 8 dari 10 rumah melebihi batas SPLN sebesar 5,8%presentase terkecil hingga 16,7% presentase terbesar
Deskripsi Lain
This study analyzes the effect of capacitor bankusage on distribution losses in the Gunung Sawur micro-hydro power plantsystem. The research was conducted to evaluate the effectiveness of capacitorbanks in improving the efficiency of the electrical distribution system byreducing reactive power losses. The analysis process began with the collectionof basic system parameters, including generator characteristics, cable types,and loads, obtained from technical specifications well direct field measurements.The collected data were used in manual calculations to determine key parameterssuch output power, efficiency, and system stability, which were thenimplemented in ETAP software to perform electrical simulations. Thesesimulations included power flow analysis, system stability, and variousoperational scenarios both with and without the use of capacitor banks. Fromthe results of the voltage regulation analysis, 8 out of 10 houses exceeded theSPLN limit, ranging from the smallest percentage of 5.8% to the largestpercentage of 16.7%
Kontributor | : Dian Neipa Purnamasari, S.ST., M.Tr.T.;Deni Tri Laksono, S.Pd., M.T. |
Tanggal tercipta | : 2025-09-15 |
Jenis(Tipe) | : Text |
Bentuk(Format) | |
Bahasa | : Indonesia |
Pengenal(Identifier) | : TRUNOJOYO-Tugas Akhir-38130 |
No Koleksi | : 210431100082 |
Sumber :
Universitas Trunojoyo Madura
Relasi/Tautan:
Rugi-Rugi Distribusi Pada Jaringan Pembangkit Listrik
Ketentuan (Rights) :
2025











Tidak ada !